Witness Testing

After routine tests completion and upon request, Project Managers schedule a Factory Acceptance Test (FAT) where customers during which our clients witness the system's full accordance with requirements.

Our test bay is fully equipped to ensure foolproof testing:

  • 1 MVA upstream transformer
  • 16 test bays, from 100 to 1000 A
  • 1.5 MW load bank for full load tests

All testing equipments and infrastructures are regurarly checked and upgraded in order to ensure the highest degree of safety during the Factory Acceptance Test (FAT).
Furthermore, a lounge with dedicated meeting rooms is available for customers visiting our premises.

  • Factory Acceptance Test schedule available at an early stage of the project
  • Inspection procedure provided prior to the factory acceptance test
  • Specific tests are possible to ensure full compliance with customer’s requirements
  • Dedicated inspection report is delivered with full technical testing details as well as customer’s comments